|
1
|
|
|
2
|
|
|
3
|
|
|
4
|
- Address Critical Needs of the School
- Address Regulatory Issues
- Reduce Operating & Maintenance Costs
- Improve classroom environment and functionality
- Minimize the cost to the taxpayer
- Minimize Disruption to the Student Body
- Develop a project that addresses both long and short-term needs
|
|
5
|
- Replacement of the Heating and Air Circulation systems
- Upgrading of the Electrical System
- Relocation of the Electrical Transformers outside the building
- Removal of all Asbestos related materials
- Repairs to or Replacement of the Leaking Roof Areas
- Upgrade the fire safety system
- Bring full 2way communication to all classrooms
|
|
6
|
- Make the school Handicapped Accessible
- Bring the building up to state building code standards
- Addition of a sprinkler system (required)
- Separation of water and electrical systems in maintenance closet. (also
a building code issue
|
|
7
|
- Reduce the need for emergency repairs
- Make the building more energy efficient
- Reduce the need for costly service contracts
|
|
8
|
- Create an appropriate Library/Computer Lab
- Improve classroom environment, lighting, and functionality
- Add wiring for computer networking, Internet, & Cable to each
classroom
- Add appropriate number of electrical outlets
|
|
9
|
- Plan a school that is “right sized” and maximize all usable space.
- Make spaces flexible for multiple use.
- Maximize available SBA funds.
|
|
10
|
- Finished school building will provide for all current and future needs
of the program
- School will last for another 50 years.
|
|
11
|
- After town meeting the committee felt there were 3 major reasons for why
the $7,800,000 project which addressed the school’s needs failed:
- The cost was too great
- There was a question as to if and/or when we would get the SBA funding
- The Voters were not sure they were presented with the right plan i.e.
because it still resulted in a school they felt was too big or
inefficient
|
|
12
|
- At this point the committee revisited all the previously reviewed
options. (Renovation, New School)
- We concluded that we still did believe a completely new school was going
to be less expensive in the end.
- We decided to look at a combination project which would keep the best of
the current school building and construct new space to address any
additional needs
|
|
13
|
- We concluded that the single story wings, added to the building in the
early 1960s, were the least efficient and in need of the most amount of
work (i.e. window replacements, roof repairs)
- These wings have the inefficient long and wide hallways, level changes
requiring lifts, extensive flat roof to repair, and small classrooms.
- These wings although newer were built at a time when fuel efficiency was
not a major consideration
|
|
14
|
- We came up with a design that will require:
- Demolition of the Junior High
wings on the north side and the single story addition on the south side
of the building
- New construction of a 16,600 sq ft, 2-story addition on the south side
of the building to address the remaining space needed.
- This achieves a net reduction of 6,400 sq ft in the overall size of the
current building
- Final building size: 43,600 sq ft
|
|
15
|
|
|
16
|
|
|
17
|
|
|
18
|
- Using 240 students as the size student population we need to build a
school for, the DOE would allot 38,400 sq ft as the size of our
school. (The 240 Students was
arrived at by a study done by Merrimac Educational Associates for our
initial submission to the SBA and averaged projections and existing data
from 1990-2013)
- If you take into consideration the facts that we have an over sized gym
and cafeteria for an elementary school and designated space for a
preschool program, the school is in line with the DOE figure.
|
|
19
|
|
|
20
|
- The previously approved funds from the SBA amounts to $1,880,350 for
construction costs.
- In an effort to clear the list before opening up the new program, the
state intends to pay out all moneys in a lump sum by Fiscal Year 2008.
- Committee Member and Town Administrator Mark Cullinan has met with the
director of the new MSBA program and has received confirmation that
Nahant will remain eligible for all the funds previously approved even
though we have changed the project.
|
|
21
|
- New Ramp at main entrance to the building
- Hallway from the gym to the cafeteria and library will be ramped to
alleviate the need for chair lifts.
- Bathrooms will fully renovated and made Handicap accessible
- Addition of an elevator in the center of the school in the newly
constructed area
|
|
22
|
|
|
23
|
|
|
24
|
- All classrooms will have new lighting, lockers, white boards, and window
blinds.
- All classrooms will be painted, have new flooring, and an appropriate
amount of storage
- All classrooms will have new wiring for additional outlets, internal
networking, internet, and cable access.
|
|
25
|
|
|
26
|
- All hallways and administrative spaces will be painted and have new
flooring.
- Roof repairs as needed.
- Thorough exterior masonry restoration
- The building will be brought into compliance with all State and Federal
Regulations.
|
|
27
|
|
|
28
|
- Library and Computer Lab in old locker room space
- 2 classrooms on each floor will have a folding partition to join the
rooms into 1 large space giving added flexibility.
- Separate Art and Music rooms central in the building that can be used by
the SPED department or others when not in use during the regular school
day
- Bathrooms for the staff on both floors
|
|
29
|
|
|
30
|
- Full replacement of Boilers and distribution pipes
- New unit ventilators, roof exhaust fans, and associated controls
throughout the building
- Automated and programmable temperature controls with ability to monitor
and control offsite
- All equipment will be energy efficient and up to today's technology
standards
- The Library, Administrative Space, and the Cafeteria will have the
ability to be air conditioned.
|
|
31
|
- New Main Electrical Service Panel and associated distribution panels
throughout the building.
- All existing wiring will be replaced and new wiring added as needed for
additional outlets and lighting.
- Addition of outdoor lighting for security and proper illumination
- Emergency lighting throughout the building utilizing regular lighting
fixtures
|
|
32
|
- Telephone System (25K previously appropriated)
- Master Clock System/PA System
- Fire Alarm system with audible and visual alarms
- Sprinkler System
- Security system with door monitoring, security access pad, and motion
sensors
- Exit Signs throughout the building
|
|
33
|
- Due to the reduced overall square footage and increased efficiency of
the building after completion of the project, operating costs to provide
heat and electricity to the building are projected to be reduced by 40%
compared to Fiscal Year 04 and 03 actual costs.
- Square Feet Cost/Sq Ft Total Cost Difference
- Projected 43,600 1.12
$48,832
- 2003 Actual 50,000 1.70
$84,809 $35,977
- 2004 Actual 50,000 1.65
$82,264 $33,432
- Average Annual Savings without rate changes - $34,704
- (Projected is based on a heating fuel rate of $1.35/therm, electricity
rate $0.12/KWH)
|
|
34
|
- $5,000 is spent each year for regular heating system maintenance
- An average of $62,290 has been spent over the last 3 years on building
repairs to keep systems operation.
- Preventative Maintenance items for the new building would be $12,000
HVAC, $1,900 elevator inspections and maintenance, $2,000 Fire Alarm
system inspection and maintenance.
- Even if you added in $10,000 for other unforeseen items, the reduction
in maintenance cost would be 60% or approximately $40,000
|
|
35
|
- There is currently no alternate location for a licensed preschool to
operate within Nahant.
- The current trend at the DOE has put an increased importance on
preschool education and they are currently working on a Universal
Preschool Program.
- School systems with an existing preschool program are encouraged to
continue offering the service, school systems without a program of their
own are encouraged to create partnerships with a privately run program
which is what Nahant is doing right now with Periwinkle Preschool.
|
|
36
|
- Item Cost to Add into Project
- Cafeteria floor replacement $25,000
- New Traffic Pattern layout at front entrance $30,000
- Remodeling of Kitchen Area
$8,000
- Upper Level Drop Ceiling $25,800
- New Sound system in Cafeteria $15,000
- Acoustical treatment in Cafeteria $43,000
- Cafeteria and Gym painting $40,000
- Computer Hardware
$280,000
- Furniture $270,000
- Playground equipment & ground materials $30,000
|
|
37
|
- Summer 2005, Asbestos floor tile removal, relocation of electrical
transformers to outside of the building.
- Nov 2005-May 2006, Demolition of single story wing at south end of the
building and construction of New Addition
- July 2006-Aug 2006, Installation of main heat distribution lines on
existing lower level, replace boilers, renovation of existing portion of
the building. New addition is now
fully functional
- Sep 2006-December 2006, Renovation of Office Areas, New Library, and
ramps to the Cafeteria
- Jan 2006, Demolition of North Wings can begin
- Site work to be completed after spring thaw
|
|
38
|
|
|
39
|
|
|
40
|
|
|
41
|
|
|
42
|
|
|
43
|
|
|
44
|
- All Critical needs addressed
- All regulatory needs addressed
- Operating and Maintenance costs will be reduced
- Classroom environment is improved and more functional
- Overall Cost to the taxpayers of Nahant has been reduced
- Allowances have been made and will continue to be made to minimize
disruption to the students and staff during the building process
- Nahant will have a building to serve it both now and well into the
future
|
|
45
|
|